Project Remaining Budget Calculator
Reforecast a fixed-fee project using costs already incurred and the work still required, preserving overruns and a negative final margin.
Formula and cost boundary
Forecast profit = fee − cost incurred − (remaining hours × cost rate + other remaining cost)
Remaining fee after incurred cost is not cash in the bank and not permission to spend. Compare it with the independent estimate to complete. Use cost rates rather than sales rates, and include only committed scope in the agreed fee. Unapproved change orders should remain separate scenarios. A zero fee has no margin denominator even though costs and losses remain meaningful.
Worked example: Still profitable
The following inputs are hypothetical values for checking the calculation. They are not recommended prices, wages, margins or platform charges. Keep the units and period shown in each label when replacing them with your own records.
| Input | Example value |
|---|---|
| Agreed project fee | $10,000 |
| Delivery cost incurred to date | $4,000 |
| Expected remaining hours | 50 hours |
| Remaining internal hourly cost | $60/hour |
| Other remaining delivery cost | $1,000 |
| Result | Calculated value |
|---|---|
| Forecast project profit or loss | $2,000 |
| Forecast cost to complete | $4,000 |
| Fee remaining after cost incurred | $6,000 |
| Forecast margin on fee | 20% |
Using the result
Save the input set alongside the source date of each quote or cost record. Review the cost boundary before comparing this result with another report: a contribution measure may exclude overhead, and a cash measure follows payment dates. Display rounding does not change the underlying assumptions. Recalculate when an input changes; the tool does not predict future sales or collections.
Are any rates supplied automatically?
No. Numeric fields are your inputs. Example values demonstrate arithmetic only. Check your contracts and records for the amounts that apply to your business.
Why might a result be unavailable or negative?
A missing denominator or inconsistent inputs can make the calculation undefined. Those combinations are rejected or labeled explicitly. A valid negative result remains visible because it may identify a loss or cash shortfall.
Method reference: OpenStax: Operating Budgets. Checked October 22, 2026. Capacity, sales and delivery-cost budgets; no market rate assumptions.
Related calculators & guides
- Hourly vs Project Pricing: Which to Choose
- Build a Scope Budget for a Fixed-Fee Project
- Contingency vs Profit Margin in Project Quotes
- Price Revision Rounds Without Hiding the Work
- Price a Change Order from Incremental Work
- Include Subcontractors in Project Quotes
- Calculate Project Profit Margin with Clear Costs
- Estimate to Complete a Fixed-Fee Project
- Project Deposits and Milestone Cash Timing
- Build Service Package Tiers from Delivery Costs
- Review Project Pricing After Delivery
- Fixed Project Price Calculator
- Project Contingency and Margin Reference
- Fixed Project Quote Worked Example
- Freelance Pricing and Project Workbook
Report an error
Thank you! Your feedback helps us make this page better.
Could not send. Please try again.