Fixed Project Quote Worked Example
Build and reforecast a hypothetical fixed project quote from internal labor costs, outside expense, contingency and a revenue-based margin.
The hourly amount is an internal delivery cost, not a selling rate. The quote first adds a 20% contingency to the $2,500 base cost. It then divides the $3,000 budget by the 75% share of revenue available for costs. Multiplying the budget by 1.25 would produce a markup of 25%, not a margin of 25%.
Quote = (40 hours × $50 cost + $500 direct expense) × 1.20 ÷ 0.75
| Step | Calculation | Result |
|---|---|---|
| Base delivery cost | 40 × $50 + $500 | $2,500 |
| Contingency | 20% × $2,500 | $500 |
| Total cost budget | $2,500 + $500 | $3,000 |
| Quote for 25% margin | $3,000 ÷ (1 − 25%) | $4,000 |
| Planned profit | $4,000 − $3,000 | $1,000 |
| Actual delivery cost | 48 × $50 + $700 | $3,100 |
| Actual project profit | $4,000 − $3,100 | $900 |
| Actual margin | $900 ÷ $4,000 | 22.5% |
How to read and reuse this example
During delivery, the project uses 48 hours and $700 of outside expense. Its total cost reaches $3,100, exceeding the budget including contingency by $100. Because the agreed fee remains $4,000, actual profit falls from $1,000 to $900. The margin changes from 25% to 22.5%, a decrease of 2.5 percentage points.
Boundaries and exceptions
This worksheet assumes the whole fee is earned and collectible. A deposit could improve cash timing while leaving the final margin unchanged. Unapproved extra work should be shown as a separate scope scenario. Keep a record of why hours and outside expenses changed so the next quote improves its task estimates rather than simply adding an unexplained percentage.
Method reference: OpenStax: Operating Budgets. Checked October 22, 2026. Capacity, sales and delivery-cost budgets; no market rate assumptions.
Related calculators & guides
- Hourly vs Project Pricing: Which to Choose
- Build a Scope Budget for a Fixed-Fee Project
- Contingency vs Profit Margin in Project Quotes
- Price Revision Rounds Without Hiding the Work
- Price a Change Order from Incremental Work
- Include Subcontractors in Project Quotes
- Calculate Project Profit Margin with Clear Costs
- Estimate to Complete a Fixed-Fee Project
- Project Deposits and Milestone Cash Timing
- Build Service Package Tiers from Delivery Costs
- Review Project Pricing After Delivery
- Fixed Project Price Calculator
- Project Remaining Budget Calculator
- Project Contingency and Margin Reference
- Freelance Pricing and Project Workbook
Report an error
Thank you! Your feedback helps us make this page better.
Could not send. Please try again.