Chart · Break-Even
Incremental Order Decision Reference
See how setup expense and displaced contribution change a special order result and minimum offer price across five capacity scenarios.
The table compares accepting an additional 200-unit order with declining it. Every scenario uses an $18 offer and an $11 incremental unit cost. The order therefore supplies $1,400 before any additional setup or displaced work. Existing unavoidable fixed overhead is outside this decision bridge; it still belongs in the overall business profit budget. All figures are hypothetical and the capacity assumptions must be checked separately.
Incremental result = 200 × ($18 − $11) − added setup − displaced contribution
| Added setup | Displaced contribution | Incremental result | Minimum offer per unit |
|---|---|---|---|
| $0 | $0 | $1,400 | $11.00 |
| $500 | $0 | $900 | $13.50 |
| $500 | $300 | $600 | $15.00 |
| $500 | $900 | $0 | $18.00 |
| $500 | $1,000 | −$100 | $18.50 |
Interpret the result
The fourth row reaches zero incremental profit, while the fifth loses $100 compared with declining the order. That result is not the company's total net profit. Displaced contribution represents the earnings forgone on other orders, after their avoidable costs; using displaced revenue would exaggerate the sacrifice. The minimum price is a cost threshold, not evidence of the customer's willingness to pay.
Check before applying the example
Confirm delivery capacity, required setup and any genuinely forgone work before choosing a row. Do not subtract an opportunity cost again in the cash-payment schedule unless it also creates an actual payment. If the order adds equipment or a staffing commitment, include the relevant additional cost rather than an unrelated allocated overhead rate.
Use your own inputs
The calculator uses the same stated decision boundary.
-
Calculator
Special Order Incremental Profit Calculator
Compare a special order with declining it, including additional setup expense and contribution displaced…
Method reference: OpenStax: Special Order Decisions. Checked October 22, 2026. Incremental cost and capacity concepts only; no legal pricing rules or market prices are asserted.
Related calculators & guides
- Quote Validity and Cost Exposure
- Supplier Rebate Thresholds: Count the Extra Stock
- All-Units vs. Incremental Purchase Discounts
- Purchase Price Variance: Separate Price from Volume
- Material Usage Variance for Actual Good Output
- Labor Rate vs. Efficiency Variance
- Standard vs. Actual Product Cost
- Order Setup Cost in Product Quotes
- Bottleneck Product Mix with Demand Limits
- Special Order Incremental Profit
- Should You Discontinue a Product?
- Sell Now or Process Further: Incremental Value
- Rework vs. Scrap: Expected Recovery
- Warranty Allowance per Unit Sold
- Consignment vs. Wholesale Economics
Report an error
Thank you! Your feedback helps us make this page better.
Could not send. Please try again.